Title: Public Infrastructure GO Bond Project Update
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Adam Lindsay, Assistant City Manager

 

FROM:                     Byron Reeves, Deputy Public Services Director                     

 

DATE:                      December 9, 2024

 

RE:

Title

Public Infrastructure GO Bond Project Update                     

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

All                      

 

 

b

Relationship To Strategic Plan:

High Quality Built Environment

Desirable Place to Live, Work, and Recreate

 

 

Executive Summary:

City Council placed a ballot measure seeking authorization of the issuance of up to $25 million in General Obligation Bonds to support capital investments in public infrastructure on the November 8, 2022 ballot. The bond authorization measure was subsequently approved by voters for “various transportation related improvements inside and outside the corporate limits of the City, including, without limitation, street, road, mobility, sidewalk and streetscape improvements, bridges, bicycle lanes, curbs and drains, traffic controls, and greenways, and the acquisition of any related land, rights of way, and equipment”.

 

With the approval of both the City’s fiscal year 2024 and 2025 budget, $16.8 million have been appropriated by Council thus far. The following staff report will provide details, expenditures/commitments to date, and schedules of the projects these proceeds are funding.

 

 

Background: 

 

Public Infrastructure GO Bond Project Appropriations:

 

Project

Appropriated to Date

Expended/Committed to Date

Street Resurfacing

$10,958,784

$10,533,489

Sidewalk

$3,536,316

$624,350

Bike Lane

$340,000

$0

Municipal Agreements

$1,450,000

$0

Intersection Improvements

$100,000

$0

Thoroughfare Street Lighting

$50,000

$0

Safe Streets for All (SS4A)

$101,216

$0

Dam Safety & Preservation Program

$35,184

$0

Bridge Preservation Program

$208,500

$0

Total

$16,800,000

$11,157,840

 

 

 

 

 

 

Issues/Analysis: 

 

Street Resurfacing:

Street resurfacing was proposed to Council and approved to be completed in three phases on March 23, 2023. The three phases were to coincide with the FY24, FY25, and FY26 budget cycles.

 

To date $10,958,784 in funding has been appropriated with $10,533,489 being expended/committed. Phase Details are as follows:

 

GO Bond Resurfacing Phase 1

                     Effective date of contract August 2, 2023

                     Substantial Completion achieved August 9, 2024

                     Project completed October 3, 2024

                     Final Contract value - $6,964,880.65

                     Contractor: Barnhill Contracting Company

                     Total Mileage Resurfaced: 20.72

                     Streets complete listed in the attached file Proposed Street List Resurface Various Streets 2023 - Phase 2

 

GO Bond Resurfacing Phase 2

                     Effective Date of Contract July 30, 2024

                     Substantial Completion anticipated September 3, 2025 and readiness for final payment must be achieved by Oct 3, 2025

                     Contract Value: $3,673,182.11

                     Contractor: Barnhill Contracting Company

                     Total Mileage Resurfaced: 7.14

                     Streets included in this contract listed in the attached Proposed Street List Resurface Various Streets 2024 - Phase 2

                     Schedule: This contract is currently at roughly 30% completion with Barnhill preparing to shut down their plant from December 20, 2024 - January 6, 2025

 

GO Bond Resurfacing Phase 3

                     Target advertising for bid in March 2025 with a bid recommendation target of June 2025.

                     Project would be funded with $4 million in appropriations adopted with Councils FY26 budget

                     Proposed streets listed in the attached Proposed Street List Resurface Various Streets 2025 GO Bond - Phase 3

 

Sidewalks:

Sidewalk locations were proposed to Council and approved September 25 2023. The project locations were selected to complete the 2018 Pedestrian Plan and Sidewalk CIP.

 

Since the approval of the sidewalk locations by Council, the City was awarded funding from NCDOT’s Locally Administered Project Program (LAPP) for several of the approved sidewalk locations. These LAPP funds will fund up to 80% of the cost of the project with the remaining 20% of funds coming from the Public Infrastructure GO Bond.

 

To date $3,556,316 in funding has been appropriated with $624,350 being expended/committed. Project details are as follows:

 

                     Country Club Drive Sidewalk - From Murchison Road to Ramsey Street

o                     Estimated Cost $840,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Bragg Boulevard Sidewalk - From Pamalee Drive to Shaw Road

o                     Estimated Cost $640,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Bonanza Drive Sidewalk - From Yadkin Road to Santa Fe Drive

o                     Estimated Cost $100,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Bunce Road Bingham Drive Sidewalk - From Raeford Road to Bailey Lake Road

o                     Estimated Cost $800,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Bingham Drive Sidewalk - From Bailey Lake Road to Lake Ridge Road

o                     Estimated Cost $175,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Morganton Road Sidewalk Phase II - From Bonanza Road to Skibo Road

o                     Estimated Cost $750,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Skibo Road / Country Club Drive Sidewalk - From Bragg Blvd to Morganton Road

o                     Estimated Cost $1,600,000

o                     Project is 100% design state

o                     Project will receive LAPP funding. Construction cannot begin until execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Stacey Weaver Drive Sidewalk - From McArthur Road to Southland Drive

o                     Estimated Cost $145,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Santa Fe Drive Sidewalk - From Bonanza Road to Yadkin Road

o                     Estimated Cost $90,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Cliffdale Road Sidewalk Phase II - From Raeford to Rim Road

o                     Estimated Cost $700,000

o                     90% Design State

o                     Project will receive LAPP funding. Construction cannot begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Cliffdale Road Sidewalk Phase III - From Rim Road to Reilly Road

o                     Estimated Cost $650,000

o                     Project will receive LAPP funding. Design will begin upon execution of a Municipal Agreement with NCDOT.

o                     Construction anticipated to start in FY26

 

                     Old Wilmington Road Sidewalk - From Russel Street to Campbell Ave

o                     Estimated Cost $45,000

o                     Design is complete

o                     Condemnation filed for 311 Old Wilmington Road on November 15,2024.

o                     Constructed expected to be complete June 2025 (Q4 FY 25)

 

                     Rosehill Road Sidewalk at Mulranny Drive - From Mulranny Drive to Circle K Driveway

o                     Estimated Cost $18,000

o                     Design is complete

o                     Construction is anticipated to begin in December 2024

 

                     Morganton Road Sidewalk Phase I - From Bonanza Road to Murray Fork Shopping Center

o                     Estimated Cost $15,000

o                     Design is complete

o                     Construction is anticipated to begin in January 2025

 

                     Levy Drive Sidewalk - From Robeson Street to Dixon Street

o                     Estimated Cost $81,000

o                     90% Design State.

o                     Will need easement acquisition

o                     Construction is anticipated to begin July 2025

 

                     Skye Drive Sidewalk - From Morganton Road to Hull Road

o                     Estimated Cost $451,000

o                     90% Design State

o                     Will need easement acquisition

o                     Construction is anticipated to begin July 2025

 

                     Eastwood Avenue Sidewalk - From Ramsey Street to Rivercliff Road

o                     Estimated Cost $460,000

o                     70% Design State

o                     Construction is anticipated to begin October 2025

 

                     Cliffdale Road Sidewalk Phase I - From Raeford Road to Two Bale Ln

o                     Estimated Cost $60,000

o                     Design Complete

o                     Construction is anticipated to begin March 2025

 

                     Fort Bragg Road Sidewalk - From Bragg Blvd to Hobson St

o                     Estimated Cost $70,000

o                     90% Design State

o                     Will need easement acquisition

o                     Construction is anticipated to begin June 2025

 

                     Mason Street and Ray Avenue Sidewalk - Ray Ave to Arch Street

o                     Estimated Cost $100,000

o                     Design Complete

o                     Construction will begin after the completion of the Ray Ave Drainage Improvement Project.

 

                     Helen Street Sidewalk - From Stanfield Drive to Johnson Street

o                     Estimated Cost $700,000

o                     Project is advertised with bids being received December 11, 2024

o                     Construction expected to begin by March 2025, upon selection of contractor and bid award.

 

                     Breezewood Avenue Sidewalk - Purdue Drive to Southside Drive

o                     Estimated Cost $80,000

o                     Project is planned to begin in FY26

 

                     Cumberland Street Sidewalk - Ramsey Street to Murchison Road

o                     Estimated Cost $250,000

o                     Project is planned to begin in FY26

 

Bicycle Plan Project Locations:

Bicycle lane locations were proposed to Council and approved June 26, 2023. The project locations were selected from the Council adopted Bicycle Plan

 

To date $340,000 in funding has been appropriated for Bicycle Lanes. Project Details are as follows:

                     Coventry Drive (Camelot Drive to Ireland Drive)

o                     Estimated Cost $100,000

o                     Road has been recently resurfaced, markings planned April 2025

 

                     McGilvary Street (Branson Street to Robeson Street)

o                     Estimated Cost $100,000

o                     Roadway is currently being resurfaced, markings planned April 2025

 

                     Winslow Street (Southern Avenue to Rankin Street)

o                     Estimated Cost $140,000

o                     Project is currently being designed with construction anticipated in October 2025

 

Municipal Agreements:

GO Bond funding in the amount of $1,450,000 has been appropriated for Municipal Agreements. Municipal Agreements entered into with NCDOT allow for public improvements to be included on NCDOT projects at the request of the City. NCDOT constructs these improvements as part of their roadway projects and then invoices the City for 20% of the cost.

 

                     U-4405B Raeford Road (Bunce Road to Glensford Drive)

o                     Bidding Phase (Muni Agreement Signed)

o                     Estimated Cost $400,000

o                     Schedule - Spring / Summer 2025

 

                     U-5798A Gillis Hill Road (Stoney Point Road to Raeford Road) Landscape

o                     Design Phase

o                     Estimated Cost $150,000

o                     Schedule - Unknown, after Roadway Construction is Complete

 

                     U-5798B Gillis Hill Road (Stoney Point Road to Raeford Road) Sidewalk

o                     Design Phase

o                     Estimated Cost $200,000

o                     LET to Bid in late 2025

 

                     U-5798B Gillis Hill Road (Stoney Point Road to Raeford Road) Landscape

o                     Design Phase

o                     Estimated Cost $150,000

Schedule - Unknown, after Roadway Construction is Complete

 

                     U-4900 Murchison Road (I-295 to South of US 401 Bypass)

o                     R/W - Design

o                     Estimated Cost $300,000

o                     Scheduled to LET to Bid May 2026

 

                     Morganton Road Pedestrian Improvements at Intersections

o                     Design Phase

o                     Estimated Cost $250,000

o                     Scheduled to LET to Bid May 2026

 

Safe Streets for All (SS4):

Go Bond funding in the amount of $101,216 has been appropriated as the City’s portion of the Safe Streets for All Grant. The City’s portion was 20% of the grant award, which totaled $506,083.

 

With this grant, the City of Fayetteville is partnering with the Fayetteville Area Metropolitan Planning Organization (FAMPO) to produce a Roadway Safety Action Plan, which will identify opportunities to improve roadway safety and access to economic opportunities for underserved communities. Fayetteville is creating a roadway improvement action plan using the Vision Zero Safe System approach, which prioritizes the safety of all roadway users, including pedestrians and cyclists.

 

SS4A was kicked-off in September 2024 and is scheduled to take a year to complete. Final reports and deliverables are scheduled to be received September 2025.

 

Intersection Improvements:

Go Bond funding in the amount of $100,000 has been appropriated for Intersection Improvements. These funds are programmed to go towards the pedestrian improvements identified in the 2018 Pedestrian Plan for the intersection of Rosehill Road and McArthur Rd. Currently NCDOT is working within this intersection and staff is in discussion with NCDOT to expand their project to include the improvements identified in the 2018 Pedestrian Plan.

 

Thoroughfare Street Lighting:

Go Bond funding in the amount of $50,000 has been appropriated for Thoroughfare Street Lighting. For the current fiscal year, the locations this funding will be expended on are as follows:

 

                     McArthur Rd (Ramsey St to 0.53 miles North of Ramsey St)

                     Stoney Point Rd (Lakewood Rd to Grimes Rd)

                     Lakewood Rd (From Town Center Dr to Dundle Rd)

                     Dundle Rd (King Rd to Heatherbrooke Rd)

                     Andrews Rd (Ramsey St to City Limits)

 

Tentatively, project completion is scheduled for June 2025, however this is dependent upon the utility provider completing the work.

 

Dam Safety & Preservation Program:

Go Bond funding in the amount of $35,184 has been appropriated for the Dam Safety & Preservation Program. This funding will go towards repairing downstream embankment erosion at the City owned The Lakes Dam (CUMBE-021) located underneath E. Loch Haven Drive. Maintenance work is scheduled to be completed in September 2025.

 

Bridge Preservation Program:

Go Bond funding in the amount of $208,500 has been appropriated for the Bridge Preservation Program. This funding will go towards the design and construction of bridge deck repairs for bridges on Hawley Lane, Campbell Avenue, and Filter Plant Road. Design is anticipated to begin in January 2025 with construction scheduled to be completed December 2025.

 

 

 

Budget Impact: 

N/A

 

 

Options

Receive the administrative report for the Public Infrastructure GO Bond Project Updates.

 

Don not receive the administrative report for the Public Infrastructure GO Bond Project Updates and provide further direction to staff.

 

 

Recommended Action: 

Council receive the administrative report for the Public Infrastructure GO Bond Project Updates.

 

 

Attachments:

Proposed Street List Resurface Various Streets 2023 - Phase 2

Proposed Street List Resurface Various Streets 2024 - Phase 2

Proposed Street List Resurface Various Streets 2025 GO Bond - Phase 3