Title: Parks and Recreation Projects Report Card
Attachments: 1. P&R Project Report Card - Feb 5 2024
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Douglas J. Hewett, ICMA-CM, City Manager

                                          Adam Lindsay, Assistant City Manager

 

FROM:                     Michael Gibson, Parks, Recreation and Maintenance Director

Rob Stone, PE, Construction Management Director

 

DATE:                      February 5, 2024

 

RE:

Title

Parks and Recreation Projects Report Card                     

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

All                     

 

 

b

Relationship To Strategic Plan:

Goal 4: Desirable Place to Live, Work, and Recreate

 

 

Executive Summary:

City Council will be provided the status of the eight significant Parks and Recreation Bond Projects currently underway, including the Bill Crisp Senior Center, Senior Center East, McArthur Road Sports Complex, the Mazarick Tennis Center, D. Gilmore Therapeutic Center, Mable C. Smith Park, Cape Fear River Park, and Dr. Martin Luther King Jr. Park. Two of the projects include beneficial partnerships with other entities to make the most of available funding.

 

Background: 

In March 2016, Fayetteville voters passed a $35 million bond referendum for parks and recreation. To date, 15 substantial projects have been completed totaling over $15 million. The completed projects include the Bill Crisp Senior Center, D. Gilmore Therapeutic Center, Rowan Street Skateboard Park, Jordan Soccer Complex improvements, multiple splash pads, and renovations to several parks. The major projects currently in progress include Senior Center East, McArthur Road Sports Complex, the Mazarick Tennis Center, Mable C. Smith Park, Dr. Martin Luther King Jr. Park, and Cape Fear River Park. All but one of the seven remaining bond projects are in the process of design, bidding, or construction. 

 

 

Issues/Analysis: 

The major bond projects currently in progress include Senior Center East, the Mazarick Tennis Center, Mable C. Smith Park, McArthur Road Sports Complex, Cape Fear River Park, and Dr. Martin Luther King Jr. Park. The City has experienced significant construction cost increases and supply chain disruptions in the last two years, which have resulted in schedule and budget adjustments as the projects continue to move forward. The Cape Fear River Park and the McArthur Sports Fields are two projects that are currently underfunded to complete the projects as designed. The Cape Fear River Park is currently in the concept stage and is proposed as a phased approach. The McArthur Sports Complex design is complete, and staff applied for, but did not receive, the Defense Community Investment Program Federal Grant in an effort to cover the cost of construction.

 

 

Budget Impact: 

For the significant projects under design and/or construction, the current budgets are as follows:

 

Planned Use                                                                 Bond                                           Other                                                                    Total

                                                                                                         Proceeds                                          Funding                                          Projected

Senior Center East                                                               $9,197,900                                          $     27,900                                          $  9,225,800

Mazarick Tennis Center                                          $6,000,000                                          $5,500,000                                          $11,500,000

Mable C. Smith Park                                          $1,028,660                                          $1,256,660                                          $  2,285,320

Cape Fear River Park                                          $2,380,815                                                                                                         $  9,380,000

McArthur Sports Fields                                          $3,677,663                                                                                                         $19,000,000

 

Dr. Martin Luther King Jr. Park                     $   100,000                                          $4,500,000                                                 TBD

 

 

 

Options

Accept this Parks and Recreation Project report or give further direction.

 

 

 

Recommended Action: 

Staff recommends accepting the Parks and Recreation Project report.

 