Legislation Details

File #: 26-0556    Version: 2 Name:
Type: Other Items of Business Status: Agenda Ready
File created: 8/14/2026 In control: City Council Regular Meeting
On agenda: 8/24/2026 Final action:
Title: Authorization Fire Station 4 Phase 1: Site Preparation
Attachments: 1. Cumming Group_Proposal for PM Services for City of Fayetteville Fire Station #4. 7-20-26 (full binder).pdf, 2. CPOA 2019-34, 3. CPO 2027-1

TO:                                            Mayor and Members of City Council

THRU:                      Dr. Douglas J. Hewett, ICMA-CM, City Manager

 

FROM:                     Jeffrey Yates, ICMA-CM, Assistant City Manager

 

DATE:                      August 24, 2026

 

RE:Title

Authorization Fire Station 4 Phase 1: Site PreparationTitle

end

end

COUNCIL DISTRICT(S):                      

Council District(s)

 District 4                         

 

 

b

Relationship To Strategic Plan:

Supports the City's Comprehensive Community Safety priority by advancing the first phase of the Fire Station 4 building project and preparing the property for future public-safety use.

 

Executive Summary:

Staff recommends that the City Council authorize Phase 1 of the Fire Station 4 project to clear and prepare the site at Bragg Boulevard and Villagio Place for future reconstruction. The requested actions include site-preparation contracts, an agreement with Cumming Group for external project management, establishment and funding of a new capital project, and approval of the Phase 1 plan.

 

Background: 

N/A

 

Issues/Analysis: 

Phase 1 Scope:

Phase 1 will document and prepare the site, including debris clearing; backfilling; rough grading; stabilization; security; and required permits, inspections, testing, and closeout. Phase 1 ends with a safe, documented, build-ready site.

 

Project Management and Controls:

Cumming Group will provide external day-to-day project-management support. The City will retain decision, contracting, payment, and acceptance authority. The site-preparation contractor will remain responsible for safety, means and methods, environmental compliance, workmanship, schedule, quality control, and correction of deficient work.

 

Budget Impact: 

Phase 1 will be funded by appropriating approximately $1.53 million in General Obligation bond premium proceeds and transferring approximately $3.84 million remaining in the Fire Station 4 relocation project to the new project. These funds may be used for authorized Phase 1 activities.

    

Options

1.                     Approve the recommended Phase 1 actions.

2.                     Do not approve and provide staff with further direction. 

     

Recommended Action::Recommended Action

Move to approve Fire Station 4 Phase 1 site preparation; authorize the City Manager to execute the related site-preparation contracts and the Cumming Group project-management agreement; establish the new capital project, appropriate approximately $1.53 million in General Obligation bond premium proceeds, and transfer approximately $3.84 million in remaining project funds; and approve the Phase 1 plan.

end

Attachments:

Cumming Group Project-Management Scope

Capital Project Ordinance Amendment 2019-34

Capital Project Ordinance 2027-1