TO: Mayor and Members of City Council
THRU: Adam Lindsay, Assistant City Manager
FROM: Shelia Thomas-Ambat, PE, CCM, CFM, Public Services Director
DATE: May 28, 2024
RE:
Title
Stormwater ARP Projects Quarterly Update
end
COUNCIL DISTRICT(S):
Council District(s)
2 & 3
b
Relationship To Strategic Plan:
Goal 3: City Investment in Today and Tomorrow
Goal 4: Desirable Place to Live, Work and Recreate
Executive Summary:
On April 25, 2022, Council adopted a Resolution to accept American Rescue Plan (ARP) Funding in the amount of $10,550,000 from the North Carolina Department of Environmental Quality, Division of Water Infrastructure for the construction of stormwater improvement projects. The projects identified to utilize this funding were the Adam Street Drainage Improvement Project, North Street Drainage Improvement Project, Ray Avenue Drainage Improvement Project, and Sunbury Drive Drainage Improvement Project.
The following is a quarterly Administrative Report from the Public Services Department on the status of each of the projects utilizing this funding.
Background:
The North Carolina General Assembly identified the City as eligible to receive ARP funding under S.L. 2021-180 for stormwater infrastructure. The amount of the funding totals $10,550,000. The funding is being administered by the North Carolina Department of Environmental Quality’s (NCDEQ) Division of Water Infrastructure (DWI).
At the guidance of DWI, staff filled out and submitted Request for Funding Applications for multiple stormwater improvement projects for the Division to determine merit and eligibility of the projects for use of the funding. Staff was notified on February 14, 2022 that DWI had reviewed the Request for Funding and determined that the proposed projects were eligible to receive the ARP funding. The proposed projects are as follows:
• Adam Street Drainage Improvements
• North Street Drainage Improvements
• Ray Avenue Drainage Improvements
• Sunbury Drive Drainage Improvements
Staff then continued the process of completing the design of the aforementioned
Projects and submitted to DWI for their review and approval of plans and specifications.
On June 28, 2023 North Street, Ray Avenue, and Sunbury Drive received Plans and
Specifications Funding Approval from DWI. On July 24, 2023 Adam Street received
Plan and Specification Funding Approval from DWI.
Upon receiving approval from DWI, all projects have been advertised to the
public for bid opportunities and are moving forward to construction.
Issues/Analysis:
Adam Street Drainage Improvements
Scope of Project:
• The Adam Street Drainage Improvement Project will construct approximately 1,050 linear feet of storm drainage improvements with approximately 1,300 linear feet of water main replacement, and associated roadway improvements along Adam Street. The project is an upgrade to the existing storm drain system which consists of small diameter concrete pipe and limited catch basin inlets. The existing storm drain system is being removed and upsized to provide more drainage capacity to reduce localized flooding.
Completed Tasks this Quarter (and prior Quarter):
• Council approved a bid recommendation and Resolution of Tentative Award on December 11, 2023 to award contract and authorize the City Manager to execute a contract with the lowest responsive, responsible bidder, Jymco Construction Co., in the total amount of $1,495,129.00.
• City received Authority to Award from DWI on December 15, 2023
• City executed a Construction Reimbursable Agreement with PWC in the amount of $552,458.00 on February 29, 2024.
• A CPOA was approved by Council on April 8, 2024 to appropriate funding for PWC revenues.
• A Pre-Construction meeting was on April 17, 2024.
Current Schedule:
• Notice to Proceed has been issued for June 10, 2024.
Projected Tasks for Next Quarter:
• Construction activities
Ray Avenue Drainage Improvements
Scope of Project:
• The Ray Avenue Drainage Improvement Project will construct infrastructure upgrades to the existing storm drain system along Ray Avenue and Maiden Lane which consists of concrete pipe and aging/failing infrastructure. The failing storm sewer system is being removed and upsized to provide more drainage capacity to reduce localized flooding.
Completed Tasks this Quarter:
• Council approved a bid recommendation and Resolution of Tentative Award on March 25, 2024 to award contract and authorize the City Manager to execute a contract with the lowest responsive, responsible bidder, TA Loving Company dba Pipeline Utilities, Inc., in the total amount of $2,957,376.00.
• City received Authority to Award from DWI on April 17, 2024
• City executed a Construction Reimbursable Agreement with PWC in the amount of $784,206.00 on May 7, 2024.
Current Schedule:
• Construction Contract is currently being routed for execution.
• A CPOA is on tonight’s consent agenda to appropriate funding for PWC revenues and stormwater enterprise funds for cost exceeding the ARP amount.
Projected Tasks for Next Quarter:
• Schedule Pre-Construction Meeting
• Construction notifications sent to affected property owners
• Issue Notice to Proceed
• Contractor mobilization
Sunbury Drive Drainage Improvements
Scope of Project:
• The Sunbury Drive Drainage Improvement Project will construct infrastructure upgrades to the existing storm drain system along Sunbury Drive, Needham Drive, and Pleasant Loop Road which consists of concrete pipe and aging/failing infrastructure. The failing storm sewer system is being removed and upsized to provide more drainage capacity to reduce localized flooding.
Completed Tasks:
• Council approved a bid recommendation and Resolution of Tentative Award on May 13, 2024 to award contract and authorize the City Manager to execute a contract with the lowest responsive, responsible bidder, TA Loving Company dba Pipeline Utilities, Inc., in the total amount of $7,024,174.00.
Current Schedule:
• City is submitting items to DWI to receive an Authorization to Award
• City is working to execute a Construction Reimbursable Agreement with PWC in the amount of $1,618,475.00
Projected Tasks for Next Quarter:
• Bring before Council a CPOA to appropriate funding for PWC revenues and stormwater enterprise funds for cost exceeding the ARP amount.
• Execute construction contract between the City and TA Loving
• Schedule Pre-Construction Meeting
• Issue Notice to Proceed
North Street Drainage Improvements
Scope of Project:
• The North Street Drainage Improvement Project will construct infrastructure upgrades to the existing storm drain system along North Street, Ingram Street, and Sewell Street which consists of concrete pipe, corrugated metal pipe and aging/failing infrastructure. The failing storm sewer system is being removed and upsized to provide more drainage capacity to reduce localized flooding.
Completed Tasks:
• A bid recommendation and Resolution of Tentative Award is included on tonight’s consent agenda to award contract and authorize the City Manager to execute a contract with the lowest responsive, responsible bidder, Lanier Construction Co, Inc., in the total amount of $3,913,260.00
Current Schedule:
• City is submitting items to DWI to receive an Authorization to Award.
• City is working to execute a Construction Reimbursable Agreement with PWC in the amount of $283,5250.00
Projected Tasks for Next Quarter:
• Bring before Council a CPOA to appropriate funding for PWC revenues and stormwater enterprise funds for cost exceeding the ARP amount.
• Execute construction contract between the City and Lanier Construction Co.
• Schedule Pre-Construction Meeting
• Issue Notice to Proceed
Projects are on schedule to expend all ARPA funds prior to the December 31, 2026 deadline.
Budget Impact:
There is no impact to the City’s General Fund. Projects are funded with ARP funding from the State Fiscal Recovery Fund established in S.L. 2021-180.
Any cost over ARP provided funds for City items are being funded with prior project appropriations utilizing stormwater enterprise funds.
PWC items related to their utility upgrades are not eligible for ARP funding and will be PWC’s responsibility to fund. The City will pay the contractor invoices as they are received and will, in turn, bill PWC.
Options:
1) Receive the Stormwater ARP Projects Quarterly Update report.
2) Do not receive the Stormwater ARP Projects Quarterly Update report and provide further direction to staff.
Recommended Action:
Staff recommends Council receive the Stormwater ARP Projects Quarterly Update
report.
Attachments: