Title: PWC - Approve Bid Recommendation - Phase V Annexation Project XV Construction Area 32 East Sections I
Attachments: 1. Action Request - Phase V Annexation Project XV Const Area 32E Sections II 2

TO:                                            Mayor and Members of City Council

THRU:                      Timothy L. Bryant, CEO/General Manager

                                          Fayetteville Public Works Commission

 

FROM:                     Fayetteville Public Works Commission

 

DATE:                      April 13, 2026

 

RE:Title

PWC - Approve Bid Recommendation - Phase V Annexation Project XV Construction Area 32 East Sections ITitle

end

end

COUNCIL DISTRICT(S):                      

Council District(s)

 All                     

 

 

b

Relationship To Strategic Plan:

High Quality Built Environment

 

Executive Summary:

Bids were received for the construction of Phase V Annexation Project XV Construction Area 32 East Sections II to Vortex Civil Infrastructure, LLC, Durham, NC, the lowest responsive, responsible bidder and in the best interests of PWC in the total amount of $7,205,686.00.

 

Background: 

The Fayetteville Public Works Commission, during the meeting on March 25, 2026, approved the award recommendation for construction of Phase V Annexation Project XV Construction Area 32 East Sections II to Vortex Civil Infrastructure, LLC, Durham, NC, the lowest responsive, responsible bidder and in the best interests of PWC in the total amount of $7,205,686.00 and forward to City Council for approval.

 

Bid Date: January 28, 2026

 

Conforming Bidders                                                                                    Total Price

Vortex Civil Infrastructure, LLC, Durham, NC                                                             $7,205,686.00

T.A. Loving Company, Goldsboro, NC                                                                        $8,005.000.00

Moffat Pipe, Inc, Wake Forest, NC                                                                        $9,504,424.00

 

Issues/Analysis: 

The bid notice was advertised through our usual channels on December 12, 2025, with a bid opening date of January 28, 2026. Bids were solicited from three (3) vendors, and three (3) bids were received. SDBE/ SLS Participation - Vortex Civil Infrastructure, LLC, Durham, NC,                     is not a small local supplier or SDBE business. Vortex Civil Infrastructure, LLC anticipates $1,153,314.00 of SDBE spend for boring needs.

.

Budget Impact: 

Phase V Annexation Project XV Construction Area 32 East Sections II is budgeted in the following account strings:

Sewer: 059.0000.0435.1903815-13.800050CPR1000130

Water: 059.0000.0435.2509376-09.700030CPR1000095

    

Options

N/A

     

Recommended Action::Recommended Action

The Fayetteville Public Works Commission recommends the Fayetteville City Council approve the award recommendation for construction of Phase V Annexation Project XV Construction Area 32 East Sections II to Vortex Civil Infrastructure, LLC, Durham, NC, the lowest responsive, responsible bidder and in the best interests of PWC in the total amount of $7,205,686.00 and authorize the CEO/General Manager of the Fayetteville Public Works Commission to execute for that purpose the contract for its construction.

end

Attachments:

Bid Recommendation - Phase V Annexation Project XV Construction Area 32 East Sections II