TO: Mayor and Members of City Council
THRU: Timothy L. Bryant, CEO/General Manager
Fayetteville Public Works Commission
FROM: Fayetteville Public Works Commission
DATE: April 13, 2026
RE:Title
PWC - Adopt Resolution for the Tentative Award of Bid Contract for P.O. Hoffer and Glenville Lake Water Treatment Facility Post-Filter GAC Adsorption Facilities Contract No.67 (PWC2425049)Title
end
end
COUNCIL DISTRICT(S):
Council District(s)
All
b
Relationship To Strategic Plan:
High Quality Built Environment
Executive Summary:
The Fayetteville Public Works Commission adopted PWC Resolution - PWC2026.07 for Tentative Award of Bid Contract to Harper General Contractors, Inc., Greenville, SC in the total bid amount of $133,653.00, and requests The Fayetteville City Council adopt a similar resolution approving the same.
Background:
The Fayetteville Public Works Commission, during the meeting on March 25, 2026, adopted PWC Resolution - PWC2026.07, approving the tentative award of Bid Contract to Harper General Contractors, Inc., Greenville, SC in the total bid amount of $133,653.00, the lowest responsive, responsible bidder and in the best interests of PWC and requests The Fayetteville City Council adopt a similar resolution approving the same.
Bid Date: February 26, 2026
Bidders Total Price
Harper General Contractors, Inc, Greenville, SC $133,653,000
T.A. Loving Company, Goldsboro, NC $164,118,982
M.B. Kahn Water Works, LLC, Columbia, SC $169,628,225
Issues/Analysis:
N/A
Budget Impact:
216.0000.0435.2409182-05.820090CPR1000531
216.0000.0435.2409183-05.820090CPR1000532
Options:
N/A
Recommended Action::Recommended Action
The Fayetteville Public Works Commission recommends the Fayetteville City Council approve the attached resolution authorizing tentative award of bid contract to Harper General Contractors, Inc., Greenville, SC in the total amount of $133,653.00, the lowest responsive, responsible bidder. Such approval is made contingent upon the approval of the North Carolina Department of Environment Quality. The City Council authorizes the CEO/General Manager of the Fayetteville Public Works Commission to execute for that purpose the contract for its construction.
end
Attachments:
PWC Resolution - PWC2026.07 Tentative Award of Bid Contract; City Resolution - Tentative Award of Bid Contract PO Hoffer and Glenville Lake