Legislation Details

File #: 24-4234    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 9/11/2024 In control: City Council Regular Meeting
On agenda: 9/23/2024 Final action: 10/15/2025
Title: Adoption of Capital Project Ordinance to appropriate $1,450,000 of Public Infrastructure GO Bond funds for NCDOT Municipal Agreements
Attachments: 1. CPO 2025-24
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Adam Lindsay, Assistant City Manager

 

FROM:                     Sheila Thomas-Ambat, Public Services Director

Kimberly Leonard, CLGBO, CLGFO, CPA, MPA, Budget & Evaluation Director

 

DATE:                      September 23, 2024

 

RE:

Title

Adoption of Capital Project Ordinance to appropriate $1,450,000 of Public Infrastructure GO Bond funds for NCDOT Municipal Agreements                      

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

3, 4, 5, 7, & 9                      

 

 

b

Relationship To Strategic Plan:

Goal 3: High Quality Built Environment

Goal 4: Desirable Place to Live, Work and Recreate

 

 

Executive Summary:

Council is asked to adopt Capital Project Ordinance (CPO) 2025-24 to appropriate $1,450,000 of Public Infrastructure GO Bond funds for projects associated with NCDOT Municipal Agreements.

 

 

Background: 

As part of the FY25 budget, Council approved $1,450,000 for NCDOT Municipal Agreement projects to be funded utilizing Public Infrastructure GO Bond funds. The projects to be funded utilizing these funds are as follows:

•                     U-4405B Raeford Road sidewalks

•                     U-5798A Gillis Hill Road landscape

•                     U-5798B Gillis Hill Road sidewalks

•                     U-5798B Gillis Hill Road landscape and irrigation

•                     U-4900 Murchison Road sidewalks

•                     pedestrian improvements at intersections along Morganton Road (signals, sidewalks, ADA ramps)

 

 

 

 

Issues/Analysis: 

None

 

 

 

Budget Impact: 

There is no impact to the General Fund. Funds associated with this CPO were budgeted in FY25 utilizing Public Infrastructure GO Bond funds.

 

 

Options: 

1.                     Adopt Capital Project Ordinance (CPO) 2025-24 to appropriate $1,450,000 of Public Infrastructure GO Bond funds for projects associated with NCDOT Municipal Agreements. 

 

2.                     Do not adopt the CPO 2025-24 and provide further direction to staff. 

 

 

 

Recommended Action: 

Staff recommends Council Adopt Capital Project Ordinance (CPO) 2025-24 to appropriate $1,450,000 of Public Infrastructure GO Bond funds for projects associated with NCDOT Municipal Agreements.

 

 