City of Fayetteville
File #: 24-4343    Version: 2 Name:
Type: Consent Status: Agenda Ready
File created: 11/15/2024 In control: City Council Regular Meeting
On agenda: 11/25/2024 Final action:
Title: PWC - Frame 5 Gas Turbine Compressor Discharge Casing Replacement Bid Recommendation
Attachments: 1. Bid Recommendation - Frame 5 Gas Turbine Compressor
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Timothy L. Bryant, CEO/General Manager

Fayetteville Public Works Commission

 

FROM:                     Fayetteville Public Works Commission

 

DATE:                      November 25, 2024

 

RE:

Title

PWC - Frame 5 Gas Turbine Compressor Discharge Casing Replacement Bid Recommendation                       

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

All                     

 

 

b

Relationship To Strategic Plan:

High Quality Built Environment

 

Executive Summary:

Bids were received for the Frame 5 Gas Turbine Compressor Discharge Casing Replacement. The lowest responsive, responsible bidder and in the best interest of PWC is Turbine Services, Ltd. Saratoga Springs, NY, in the total amount of $345,000.00.

 

Background: 

The Fayetteville Public Works Commission, during the meeting on November 13, 2024, approved purchase award recommendation for the Frame 5 Gas Turbine Compressor Discharge Casing Replacement to Turbine Services, Ltd., Saratoga Springs, NY, the lowest responsive, responsible bidder and in the best interests of PWC, in the total amount of $345,000.00, and forward to City Council for approval.

 

Bids were received October 24, 2024, as follows:

 

Conforming Bidder                                                                                                                                                                        Total Cost

 

Turbine Services, Ltd., Saratoga Springs, NY                                                                                    $345,000.00

Turbine Technology Services, Orlando, FL                                                                                    $426,543.21

 

 

Issues/Analysis: 

The bid notice was advertised through our usual channels on October 15, 2024, with a bid opening date of October 24, 2024. Bids were solicited from sixteen (16) vendors, and two (2) bids were received. MWDBE/SLS Participation: Turbine Services, Ltd, Saratoga Springs, NY, is not a small local or MWDBE business and intends to self-perform the contract in its entirety.

 

 

Budget Impact: 

The Frame 5 Gas Turbine Compressor Discharge Casing Replacement is budgeted in account string 001.0170.0435.0000000-00.343000.00000.CPR1000567

 

 

Options

N/A

 

 

Recommended Action: 

The Fayetteville Public Works Commission recommends that City Council approve the bid recommendation to award bid for the Frame 5 Gas Turbine Compressor Discharge Casing Replacement to Turbine Services, Ltd., Saratoga Springs, NY, the lowest responsive, responsible bidder and in the best interests of PWC, in the total amount of $345,000.00, and authorize the CEO and General Manager of the Fayetteville Public Works Commission to execute for that purpose the contract for its purchase.

 

Attachments:

Bid Recommendation - Frame 5 Gas Turbine Compressor Discharge Casing Replacement