Skip to main content
City of Fayetteville
File #: 25-4653    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 5/16/2025 In control: City Council Regular Meeting
On agenda: 5/27/2025 Final action:
Title: Authorize Settlement and Final Payment to SfL+a Architects for work completed on the Senior Center East Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Adam Lindsay, Assistant City Manager

                                          Jeffrey Yates, Assistant City Manager

 

FROM:                     Michael Gibson, Parks and Recreation Director

Kimberly Leonard, CLGFO, CLGBO, CPA, MPA, Budget and Evaluation Director

 

DATE:                      May 27, 2025

 

RE:

Title

Authorize Settlement and Final Payment to SfL+a Architects for work completed on the Senior Center East Project                      

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

District 4                     

 

 

b

Relationship To Strategic Plan:

Goal III: The City of Fayetteville will be a city invested in Today and Tomorrow.

Goal IV: The City of Fayetteville will be a highly desirable place to live, work, and recreate.

Goal V: The City of Fayetteville will be a financially sound city providing exemplary city services.

 

 

Executive Summary:

Senior Center East opened its doors in May 2024. Since that time, it has welcomed more than 69,720 visitors. The total project cost was $9.2 million. As part of the closeout of the project, the City pays the final invoices. To close out the architectural contract,  $211,079 is due. The project account currently has $97,973. Therefore, an additional $113,106 is needed.

 

City Council is asked to adopt Capital Project Ordinance Amendment (CPOA) 2025-48 to appropriate the needed $113,106 from the Parks & Recreation Bond Fund unassigned fund balance.

 

Background: 

The City Attorney’s Office and the Construction Management Division have been working with SfL+a to close out the contract for architectural services. As part of the process, a thorough analysis of the pay applications, contract, and change orders was conducted.

 

During that review and through negotiations with SfL+a, it was determined that the City owes $211,079 for work completed. The remaining balance in the project is $97,973, resulting in a shortfall of $113,106 needed to close this contract.

 

The additional funding will come from the Parks and Recreation Bond Fund’s available unassigned fund balance. 

 

 

Issues/Analysis: 

During review and through negotiations with SfL+a, it was determined that the City owes $211,079 for work completed. The remaining balance in the project is $97,973, resulting in a shortfall of $113,106 needed to close this contract.

 

 

Budget Impact: 

The current available Parks & Recreation Bond Fund unassigned fund balance will be reduced by $113,106.

 

 

Options

Adopt Capital Project Ordinance Amendment (CPOA) 2025-48 to approve the final settlement and appropriate the funding or to instruct the City Attorney.

Reject Capital Project Ordinance Amendment 2025-48 and provide further direction to staff.

 

 

Recommended Action: 

Staff recommends that Council move to adopt Capital Project Ordinance Amendment 2025-48 to approve the final settlement and appropriate an additional $119,602 from the Parks and Recreation Bond Fund Balance.

 

 

Attachments:

CPOA 2025-48