Skip to main content
City of Fayetteville
File #: 26-0075    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 1/29/2026 In control: City Council Regular Meeting
On agenda: 2/9/2026 Final action: 2/10/2026
Title: PWC- Approve Recommendation to Reject Non-Conforming Bids - Three Phase Padmount Transformers
Attachments: 1. Recommendation - Three Phase Padmount Transformers

TO:                                            Mayor and Members of City Council

THRU:                      Timothy L. Bryant, CEO/General Manager

                                          Fayetteville Public Works Commission

 

FROM:                     Fayetteville Public Works Commission

 

DATE:                      February 9, 2026

 

RE:Title

PWC- Approve Recommendation to Reject Non-Conforming Bids - Three Phase Padmount TransformersTitle

end

end

COUNCIL DISTRICT(S):                      

Council District(s)

 All                     

 

 

b

Relationship To Strategic Plan:

High Quality Built Environment

 

Executive Summary:

Bids were received for the Three Phase Padmount Transformers. All bids were non-conforming to PWC’s bid submittal requirements and were rejected

 

Background: 

The Fayetteville Public Works Commission, during the meeting on January 28, 2026, approved recommendation to reject non-conforming bids for the Three Phase Padmount Transformers and forward to City Council for approval.

 

Bids received September 9, 2025, as follows:

 

Non-Conforming Bidders

 

AR Transformers Inc., Las Vegas, NV

Calvary Energy LLC, Warrendale, PA

Eagelerise Distribution Inc., Temple City, CA

Hyundai Corporation, Torrance, CA

JST Power Equipment, Inc., Lake Mary, FL

KLLEN Group America Inc., Simpson, NC

NexGen Power, Inc., Gardena, CA6016

Meta Power Solutions LLC, Lake Park, FL

MVA Power, Inc., Montreal, QC, Canada

Premier Transformer LLC, Princeton, NJ

PulseMac Solutions, San Antonio, TX

The Tarheel Electric Membership, Raleigh, N.C.

ULS Corporate Inc., Katy, TX

Utility Sales Associates, Midlothian, VA

Wesco, Clayton, NC                     

 

Issues/Analysis: 

The bid notice was advertised through our usual channels on August 15, 2025, with a bid opening date of September 9, 2025. Bids were solicited from four (4) vendors, and sixteen (16) bids were received.

 

The Electric Systems Engineering and Construction Departments request the rejection of all bids received for this solicitation, as they did not conform to PWC's bid submittal and/or technical specification requirements. There are currently no plans to re-advertise for three-phase transformers.

 

Budget Impact: 

Warehouse Inventory

    

Options

N/A

     

Recommended Action::Recommended Action

The Fayetteville Public Works Commission recommends the Fayetteville City Council approve the recommendation to reject non-conforming bids for the Three Phase Padmount Transformers.

end

Attachments:

Recommendation - Three Phase Padmount Transformers