Title: Fire Station 16 - Project Delivery Approach
Attachments: 1. Project Delivery Methods. 25.5.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Adam Lindsay, Assistant City Manager, ICMA-CM

FROM: Blair Hinkle, Construction Management Capital Program Manager
Bryan Roof, Owner Advisor/Project Executive, Cumming Group

DATE: June 2, 2025

RE:
Title
Fire Station 16 - Project Delivery Approach
end

COUNCIL DISTRICT(S):
Council District(s)
District 2


b
Relationship To Strategic Plan:
Goal I: Safe & Secure Community


Executive Summary:
The Fire Station 16 project team is considering the most appropriate delivery method for the project, choosing between Construction Manager at Risk (CMAR) and Single-Prime Lump Sum. The project team, including the Owner's Advisor Cumming Group and Designer Davis Kane, recommends CMAR due to its qualifications-based selection, which may attract more contractors and ensure better project delivery through experienced bidders. This agenda item aims to introduce Cumming Group as the Owner's Advisor and seek City Council's concurrence on pursuing CMAR for the project.

Background:
Currently at around 30% design, Fire Station 16 is a two-bay, 10,500 square-foot fire station located on Cedar Creek Road. At this point, it is necessary to determine the method by which this project will be delivered - Construction Manager at Risk (CMAR) or Single-Prime Lump Sum (low bid).

As directed by Council, the Fire Station 16 project will utilize an Owner's Advisor (OA), Cumming Group, in order to assist the City's project manager in the delivery of the project. One of the elements of the OA's scope is to make a recommendation, along with the project designer, Davis Kane, on the preferred delivery method. The project team has conferred to discuss options and wishes to bring their recommendation to the City Council for concurrence.



Issues/Analysis:
The City's project team - made up of the City project manager, Owner's Advisor Cumming Group, Designer Davis Kane, and Facilities Program Manager Freese and Nichols - has reviewed ...

Click here for full text