TO: Mayor and Members of City Council

THRU: Timothy L. Bryant, CEO/General Manager
Fayetteville Public Works Commission

FROM: Fayetteville Public Works Commission

DATE: November 18, 2024

RE:
Title
PWC - Rockfish B4.9 Solar Utility Station Bid Recommendation
end

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
High Quality Built Environment

Executive Summary:
Bids were received for the construction of the Rockfish B4.9 Solar Utility. The lowest responsive, responsible bidder, in the best interest of PWC is River City Construction Inc., Washington, NC, in the total amount of $6,485,706.00.


Background:
The Fayetteville Public Works Commission, during their meeting on October 23, 2024, approved the construction award for the Rockfish B4.9 Solar Utility Station to River City Construction Inc., Washington, NC, the lowest responsive, responsible bidder, in the best interest of PWC, in the total amount of $6,485,706.00. The Commission also approved to forward this recommendation to City Council for approval.

Bid Date: October 10, 2024

CONFORMING BIDDERS TOTAL PRICE

River City Construction Inc., Washington, NC $6,485,706.00
Oral's Construction Company Inc., Maxton, NC $7,882,197.77
Axis Energy Inc., Holly Springs, NC $9,926,928.54

NON-CONFORMING BIDDER

Diversified Services & Construction LLC, Fayetteville, NC




Issues/Analysis:
The bid notice was advertised through our usual channels on September 12, 2024, with a bid opening date of October 10, 2024. Bids were solicited from two (2) vendors and four (4) bids were received. The PWC Procurement Department requests the rejection of non-conforming bids to the specified bid requirements. MWDBE / SLS Participation; River City Construction, Inc., Washington, NC is a MWDBE business. River City Construction, Inc. anticipates an estimated spend of $2,100,000...