Title: PWC - Approve Recommendation to Reject Non-Conforming Bids - Switch, Recloser Bypass, Cross Arm Assembly, 3 Phase
Attachments: 1. Recommendation - Switch, Recloser Bypass, Cross Arm Assembly, 3 Phase

TO:                                            Mayor and Members of City Council

THRU:                      Timothy L. Bryant, CEO/General Manager

                                          Fayetteville Public Works Commission

 

FROM:                     Fayetteville Public Works Commission

 

DATE:                      February 9, 2026

 

RE:Title

PWC - Approve Recommendation to Reject Non-Conforming Bids - Switch, Recloser Bypass, Cross Arm Assembly, 3 PhaseTitle

end

end

COUNCIL DISTRICT(S):                      

Council District(s)

 All                     

 

 

b

Relationship To Strategic Plan:

High Quality Built Environment

 

Executive Summary:

Bids were received for the Switch, Recloser Bypass, Cross Arm Assembly, 3 Phase. All bids were non-conforming to PWC’s bid submittal requirements and were rejected.

 

Background: 

The Fayetteville Public Works Commission, during the meeting on January 28, 2026, approved recommendation to reject non-conforming bids for the Switch, Recloser Bypass, Cross Arm Assembly, 3 Phase and forward to City Council for approval.

 

Bids received September 4, 2025, as follows:

 

Non-Conforming Bidders

 

V-Energy Sales, LLC, Columbia, SC

Wesco Distribution, Inc., Clayton, NC

 

Issues/Analysis: 

The bid notice was advertised through our usual channels on August 15, 2025, with a bid opening date of September 4, 2025. Bids were solicited from four (4) vendors, and two (2) bids were received. The Electric Systems Engineering and Construction Departments request the rejection of the bids submitted, as they did not conform to PWC's bid submittal requirements.

 

Budget Impact: 

N/A

    

Options

N/A

     

Recommended Action::Recommended Action

The Fayetteville Public Works Commission recommends the Fayetteville City Council approve the recommendation to reject non-conforming bids for the Switch, Recloser Bypass, Cross Arm Assembly, 3 Phase.