Legislation Details

File #: 26-0268    Version: 1 Name:
Type: Staff Reports Status: Agenda Ready
File created: 4/17/2026 In control: City Council Regular Meeting
On agenda: 4/27/2026 Final action:
Title: Public Infrastructure General Obligation Bond Project Update
Attachments: 1. 2026.04.27 PS GO Bond Project, 2. GO Bond Phase 1, 3. GO Bond Phase 2.pdf, 4. GO Bond Phase 3
TO: Mayor and Members of City Council

THRU: Michael Gibson, Interim Assistant City Manager

FROM: Sheila Thomas-Ambat, Public Services Director

DATE: April 27, 2026

RE:Title
Public Infrastructure General Obligation Bond Project Update
Title
end
end
COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
High Quality Built Environment
Desirable Place to Live, Work, and Recreate

Executive Summary:
The City Council placed a ballot measure seeking authorization of the issuance of up to $25 million in General Obligation Bonds to support capital investments in public infrastructure on November 8, 2022, ballot. The bond authorization measure was subsequently approved by voters for "various transportation related improvements inside and outside the corporate limits of the City, including, without limitation, street, road, mobility, sidewalk and streetscape improvements, bridges, bicycle lanes, curbs and drains, traffic controls, and greenways, and the acquisition of any related land, rights of way, and equipment".

With the approval of the City's fiscal year 2024, 2025, and 2026 budget, $22.9 million have been appropriated by the Council thus far. The following staff report will provide details, expenditures/commitments to date, and schedules of the projects these proceeds are funding.

Background:
Public Infrastructure GO Bond Project Appropriations




Issues/Analysis:
Street Resurfacing:
Street resurfacing was proposed to Council and approved to be completed in three phases on March 23, 2023. The three phases were to coincide with the FY24, FY25, and FY26 budget cycles. To date $14,958,784 in funding has been appropriated with $14,417,272.74 expended/committed. Phase Details are as follows:

GO Bond Resurfacing Phase 1
* Project completed October 3, 2024
* Final Contract Value - $6,964,880.65
* Contractor: Barnhill Contracting Company
* Total Mileage Resurfaced: 20.72

GO Bond Resurfacing Phase 2
* Proj...