TO: Mayor and Members of City Council

THRU: Adam Lindsay, Assistant City Manager

FROM: Sheila Thomas-Ambat, Public Services Director
Kimberly Leonard, CLGBO, CLGFO, CPA, MPA, Budget & Evaluation Director

DATE: June 10, 2024

RE:
Title
Authorize the City Manager to Execute a Memorandum of Agreement with the NC Department of Public Safety and Adoption of Special Revenue Fund Project Ordinance 2024-13 to Appropriate Grant Award for the Ivy & Lyon Road Drainage Improvements
end

COUNCIL DISTRICT(S):
Council District(s)
2


b
Relationship To Strategic Plan:
Goal 1: Safe and Secure Community
Goal 3: High Quality Built Environment
Goal 4: Desirable Place to Live, Work, and Recreate


Executive Summary:
The City has been awarded an Emergency Management Disaster Relief and Mitigation Grant (DRMG) for the Ivy and Lyon Road Drainage Improvements Project. The total amount of the grant is $3,500,000. Staff is seeking Council authorization for the City Manager to execute a Memorandum of Agreement (MOA) with the NC Department of Public Safety Emergency Management and adoption of Special Revenue Fund Project Ordinance (SRO) 2024-13 to appropriate funding.


Background:
The City of Fayetteville's Stormwater Division applied for and received a NCDPS Disaster Relief and Mitigation Grant for the Ivy and Lyon Road Drainage Improvement Project.

This project was identified as part of the Little Cross Creek Watershed Study and was approved by Council for project development.

The project is currently at a 90% design state and in the process of completing easement acquisition, permitting, and CLOMR review through FEMA.



Issues/Analysis:
The project includes upgrades to the existing culverts at Lyon Road and Ivy Road to increase conveyance capacity which will help alleviate upstream flooding. The proposed improvements involve replacing the dual 6-ft span x 4-ft rise concrete box culverts with larger single box culverts, providing additional embedment for ...