Title: PWC Recommendation - Approve Construction Award for the Re-advertised Water Main Replacement & Rehabilitation
Attachments: 1. Action Request Form -Readvertisement Water Main Replacement & Rehab
TO: Mayor and Members of City Council

THRU: Timothy L. Bryant, CEO/General Manager
Fayetteville Public Works Commission

FROM: Fayetteville Public Works Commission

DATE: January 12, 2026

RE:Title
PWC Recommendation - Approve Construction Award for the Re-advertised Water Main Replacement & Rehabilitation
Title
end
end
COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
High Quality Built Environment

Executive Summary:
Bids were received for the construction award for the Re-advertised Water Main Replacement and Rehabilitation. The lowest responsive and responsible bidder, and in the best interest of PWC, is Insituform Technologies LLC, Southington CT, for the total amount of $8,979,370.00.

Background:
The Fayetteville Public Works Commission, during the meeting on December 10, 2025, approved the construction award recommendation for the Re-advertised Water Main Replacement and Rehabilitation to Insituform Technologies LLC, Southington, CT, the lowest responsive and responsible bidder, and in the best interest of PWC, for the total amount of $8,979,370.00, and forward to City Council for approval.

Bid Date: September 11, 2025

CONFORMING BIDDER TOTAL PRICE
Insituform Technologies, LLC, Southington, CT $8,979,370.00

NON-CONFORMING BIDDER
Mainlining America, LLC, Livingston, NJ

Issues/Analysis:
The bid notice was advertised through our usual channels on September 11, 2025, with a bid opening date of October 16, 2025. Bids were solicited from three (3) vendors, and two (2) bids were received. Award is recommended to Insituform Technologies, LLC, Southington, CT. MWDBE / SLS Participation: Insituform Technologies, LLC, is neither a small nor local supplier, nor a MWDBE business. Insituform Technologies, LLC plans to subcontract 26.6% of this project to MWDBEs

Budget Impact:
The Re-advertised Water Main Replacement & Rehabilitation is budgeted in
217.0000.0435.2600070-11.700030...CPR1000085
...