TO: Mayor and Members of City Council
THRU: Timothy L. Bryant, CEO/General Manger
Fayetteville Public Works Commission
FROM: Fayetteville Public Works Commission
DATE: April 27, 2026
RE:Title
PWC - Approve Bid Recommendation - Coating Repairs to the 1 MG Clinton Road Elevated Water Storage Tank
Title
end
end
COUNCIL DISTRICT(S):
Council District(s)
All
b
Relationship To Strategic Plan:
High Quality Built Environment
Executive Summary:
A bid was received for the construction award for the Coating Repairs to the 1 MG Clinton Road Elevated Water Storage Tank. The lowest responsive and responsible bidder, and in the best interest of PWC, is Utility Service Co., Inc, Perry, GA, for the total amount of $600,500.00.
Background:
The Fayetteville Public Works Commission, during the meeting on April 8, 2026, approved the construction award for the Coating Repairs to the 1 MG Clinton Road Elevated Water Storage Tank to Utility Service Co., Inc, Perry, GA, the lowest responsive, responsible bidder and in the best interests of PWC in the total amount of $600,500.00, and forward to City Council for approval.
Bid Date: March 24, 2026
Conforming Bidders Total Price
Utility Service Co., Inc., Perry, GA $600.500.00
Viking Painting, LLC, LA Vista, NE $665,250.00
D&M Painting Corporation, Washington, PA $951,540.00
Issues/Analysis:
The bid notice was advertised through our usual channels on February 19, 2026, with a bid opening date of March 24, 2026. Bids were solicited from three (3) vendors, and three (3) bids were received. SDBE / SLS PARTICIPATION: Utility Service Co., Inc., Perry, GA is not a small local or SDBE business. Utility Service Co., Inc., does not anticipate any small local or SDBE spend.
Budget Impact:
Account string: 002.0620.0435.650009.9999999999
Options:
N/A
Recommended Action::Recommended Action
The Fayetteville Public Work...