Skip to main content
City of Fayetteville
File #: 26-0088    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 2/2/2026 In control: City Council Regular Meeting
On agenda: 2/9/2026 Final action: 2/10/2026
Title: Authorize the City Manager to negotiate and enter into a contract for pre-construction activities for Fire Station No. 9 Construction Manager at Risk Selection
Attachments: 1. RFQ-Construction-Manager-At-Risk-Fire-Station-9, 2. City of Fayetteville CMAR for Fire Station No. 9 Submission
TO: Mayor and Members of City Council

THRU: Jeffery Yates, Assistant City Manager

FROM: Roger Hunt, Project and Contract Manager

DATE: February 9, 2026

RE:Title
Authorize the City Manager to negotiate and enter into a contract for pre-construction activities for Fire Station No. 9 Construction Manager at Risk Selection
Title
end
end
COUNCIL DISTRICT(S):
Council District(s)
4


b
Relationship To Strategic Plan:
Goal 1: Safe and Secure Community

Executive Summary:
The attached Request for Qualifications (RFQ) for Construction Manager at Risk Services for Fire Station No. 9 Relocation was issued on December 2, 2025. Three responses were received on January 8, 2026. A selection committee ranked the three responses and chose to interview all firms. Interviews were conducted on January 21, 2026, and Swinerton is the recommended candidate

Background:
The Fayetteville Fire Department (FFD) will relocate Fire Station 9 from its current facility on Santa Fe Drive to a new facility on Bonanza Drive near the intersection of Foxfire Road (REID: 0408343586000). This property was evaluated and determined to be an optimal site. The property is currently owned by the City of Fayetteville (COF). This fire station facility is expected to be approximately 13,000 square feet which will include a minimum of 3 apparatus bays with drive through capability, individual dorm rooms, kitchen / dining / day room combination, hose storage / repair / tool room, decontamination room, gear storage room, multipurpose room, public & private
bathrooms, mezzanine for HVAC / storage, laundry room, radio / report room, fitness room, IT room, electrical room, and offices.

The project will be designed by Davis Kane architects, whose contract is in the negotiation stage. MBP is under contract as the Owner's Advisor and will assist the City's project manager in the delivery of the project.

This is the second fire station in the 2022 $60 Million Public Safety Bond progra...

Click here for full text