TO: Mayor and Members of City Council
THRU: Timothy L. Bryant, CEO/General Manager
Fayetteville Public Works Commission
FROM: Fayetteville Public Works Commission
DATE: February 9, 2026
RE:Title
PWC - Approve Bid Recommendation - BABA Galvanized Steel Transmission PolesTitle
end
end
COUNCIL DISTRICT(S):
Council District(s)
All
b
Relationship To Strategic Plan:
High Quality Built Environment
Executive Summary:
Bids were received for the purchase of BABA Galvanized Steel Transmission Poles to M. D. Henry Co., Inc., Pelham, AL, the lowest responsive, responsible bidder and in the best interests of PWC in the total amount of $3,265,995.00.
Background:
The Fayetteville Public Works Commission, during the meeting on January 28, 2026, approved the award recommendation for purchase of BABA Galvanized Steel Transmission Poles to M. D. Henry Co., Inc., Pelham, AL, the lowest responsive, responsible bidder and in the best interests of PWC in the total amount of $3,265,995.00 and forward to City Council for approval.
Bid Date: August 19, 2025
Conforming Bidders Total Price
M.D. Henry Co, Inc., Pelham, AL $3,265,995.00
Belfort Capital LLC, Louisville, OH $3,400.080.00
Meyer Utility Structures, LLC, Dallas, TX $3,519.615.00
Southland Industrial Coatings/Grid Structures, Amite City, LA $3,730,110.00
Nucor Tower & Structures, Rock Hill, SC $3,831,109.80
Valmont Industries, Valley, NE $4,197,855.00
Non-Conforming Bidders
Cecil Energy Structures, Birmingham, MI
Wesco Distribution, Inc, Clayton, NC
Issues/Analysis:
The bid notice was advertised through our usual chann...
Click here for full text