City of Fayetteville
File #: 18-103    Version: 1 Name:
Type: Other Items of Business Status: Agenda Ready
File created: 3/6/2018 In control: City Council Special Meeting
On agenda: 3/7/2018 Final action:
Title: Stadium Construction Manager At Risk ("CM@R") Contract With Barton Malow Third Amendment
Attachments: 1. 2018 FB Amendment No. 3 Exhibit D
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Douglas J. Hewett, ICMA-CM, City Manager

FROM: Kristoff Bauer, Deputy City Manager

DATE: March 7, 2018

RE:
Title
Stadium Construction Manager At Risk ("CM@R") Contract With Barton Malow Third Amendment
end

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
Goal 4: Desirable Place to Live, Work and Recreate


Executive Summary:
The CM@R contract with Barton Malow authorize a "pre-construction" scope of work. The standard next step would be to execute a Guaranteed Maximum Price ("GMP") amendment that would set the construction price and fees and authorize the execution of subcontracts. The Council authorized the first GMP amendment on November 27, 2017. Concrete work, while included in the initial bid package, was excluded in order to allow for a rebid. The second GMP, approved January 22, authorized the concrete scope. The final GMP amendment is scheduled for consideration March 19th. The third GMP amendment, attached, provides limited funding authorization to avoid any project delays as the final GMP is being finalized.


Background:
The Council has taken several steps along the path of constructing a minor league baseball stadium and entertainment venue including:
* The approval of a financing plan for stadium construction,
* The execution of a thirty year operating agreement with the Astros,
* The Initiation of project design after selecting and contracting with the project architect,
* The adoption of capital project ordinance to support construction
* The execution of a CM@R contract with Barton Malow, and
* The execution of a Downtown Development Agreement with PCH.

The Astros agreement requires the stadium to be completed in advance of the 2019 baseball season.

The initial scope of work authorize in Barton Malow's contract is for the "pre-construction" phase of the project. This focuses on cost estimation, managing the schedule, subcontractor outreach, ...

Click here for full text