TO: Mayor and Members of City Council
THRU: Kristoff T. Bauer, Deputy City Manager
FROM: Rob Stone, P.E., Director of Public Services
DATE: May 7, 2018
RE:
Title
NCDOT presentation on a proposed Cliffdale Road widening project between Morganton Road and McPherson Church Road
end
COUNCIL DISTRICT(S):
Council District(s)
5, 9
b
Relationship To Strategic Plan:
Goal IV: Desirable place to Live, Work and Recreate
Executive Summary:
NCDOT is proposing a Transportation Improvement Project, U-4404, to widen Cliffdale Road between Morganton Road and McPherson Church Road. Planning efforts for the project are beginning and the project is scheduled to begin right of way acquisition in 2022 and begin construction in 2024. A preliminary design public meeting will be scheduled in late summer/early fall of 2018.
Background:
Cliffdale Road between Morganton Road and McPherson Church Road is currently a two lane roadway. A project has been identified to widen this section of Cliffdale Road through a joint planning effort by NCDOT and the Fayetteville Area Metropolitan Planning Organization. NCDOT is currently updating traffic counts and traffic projections, gathering field data and performing surveys for the project. NCDOT is anticipating a preliminary design public meeting in late summer/early fall 2018 and their project schedule has accounted for heavy public involvement and engagement throughout the planning process.
Issues/Analysis:
This is an informational item.
Budget Impact:
N/A
Options:
N/A
Recommended Action:
Information Only
Attachments:
Map of planned NC DOT Projects on Cliffdale Road
Cliffdale Road Analysis