TO: Mayor and Members of City Council

THRU: Kristoff Bauer, Deputy City Manager

FROM: Rob Stone, PE, Engineering & Infrastructure Director

DATE: June 11, 2018

RE:
Title
Bid Recommendation - Legend Ave Roadway Improvements Phase I
end

COUNCIL DISTRICT(S):
Council District(s)
District 9


b
Relationship To Strategic Plan:
High Quality Built Environment


Executive Summary:
Bids were received for the contract for the first phase of the roadway improvements at Legend Ave. The recommended lowest responsive, responsible bidder is Highland Paving, Fayetteville, NC, in the total amount of $694,721.


Background:
The roadway improvements at Legend Ave were identified and approved as part of the Capital Improvements Program. Due to right-of-way and easement issues related to the connection nearest to Skibo Rd, the project was re-designed and split into two separate phases so construction could begin on the section intersecting Sycamore Dairy Rd. This particular phase will provide street widening, sidewalks, wet pond and associated infrastructure at the intersection approach to Sycamore Dairy Rd. The contract was originally advertised for bids on April 16, 2018 with bids due on May 17, 2018. Only two bids were received and the contract had to be re-advertised.

Bids were received on May 30, 2018 as follows:

Bidders Total Cost

Highland Paving, Fayetteville, NC $ 694,721
Lanier Const, Snowhill, NC $ 996,077.75
Billy Bill Grading, Fayetteville, NC $ 1,213,297.59

The design for the remainder of the project is expected to be completed by July, 2018, with the project construction expected to be advertised for bid in September, 2018, and project completion is expected in late spring / early summer, 2019.


Issues/Analysis:
Bids were received from three contractors as outlined above. The lowest bidder, Highland Paving, is recommended.


Budget Impact:
The Engineer's construction estimate for this phase of the project is $744,804.50. The budge...