Title: Lake Rim Aquatic Center Preliminary Design
Attachments: 1. Lake Rim Pool - Schematic Site A - 10-03-18, 2. Lake Rim Pool - Schematic Site B - 10-03-18
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Telly Whitfield, PhD., Assistant City Manager

 

FROM:                     Michael Gibson, Parks, Recreation, and Maintenance Director

 

DATE:                      November 5, 2018

 

RE:

Title

Lake Rim Aquatic Center Preliminary Design                     

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

                     

 

 

b

Relationship To Strategic Plan:

Goal 4: Desirable Place to Live, Work and Recreate

 

 

Executive Summary:

City Council approved funding of a new aquatic center to be constructed at Lake Rim Park. Preliminary design concepts for the project were created by Gordon Johnson Architecture. Concepts are attached for review and approval.

 

 

Background: 

City Council appropriated funding for a new aquatic center and selected Lake Rim Park, along Old Raeford Road, as the location for the facility. Staff selected a design firm through a competitive bid process and began work with Gordon Johnson Architecture to create two potential options for Council review. Design concepts were created to ensure the design meets programming needs as well as budget constraints.

 

Schematic Design A:

                     7,000 s.f. of pool space

                     Pool slide

                     Pool play structure

                     Splash features

                     Bath/Concession/Filter buildings

 

Schematic Design B:

                     8,500 s.f. of pool space

                     Pool slide

                     Pool play structure

                     Bath/Concession/Filter buildings

 

 

 

 

 

Issues/Analysis: 

N/A

 

 

Budget Impact: 

N/A

 

 

Options

1) Approve a design concept to move forward to the Schematic Design Phase

2) Do not adopt approve a design concept and provide additional direction to staff.

 

 

 

Recommended Action: 

Staff recommends that Council approve a design concept to move forward to the Schematic Design Phase.

 

 