Title: Award Contract for Construction of an Outdoor Family Aquatics Center at Lake Rim Park
Attachments: 1. Construction Contract_M and E Contracting_Lake Rim Pool.pdf, 2. M-E SDBE Affidavit D_Lake Rim Pool.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Kristoff Bauer, Deputy City Manager

 

FROM:                     Joseph Staton, Project Manager

 

DATE:                      February 25, 2019

 

RE:

Title

Award Contract for Construction of an Outdoor Family Aquatics Center at Lake Rim Park                      

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

7                      

 

 

b

Relationship To Strategic Plan:

Goal 4 - The City of Fayetteville will be a highly desirable place to live, work and recreate with thriving neighborhoods and a high quality of life for its citizens.

 

 

Executive Summary:

The Council is asked to authorize the execution of a contract for construction of an Outdoor Family Aquatics Center to be located at Lake Rim Park.  The lowest responsive, responsible bidder, M&E Contracting, Inc., is recommended.

 

Background: 

Formal bids for construction of the Outdoor Family Aquatic Center were received February 5, 2019 as follows:

 

M & E Contracting, Inc.                                           $2,414,393.00

Player, Inc.                                                                                    $2,504,700.00

 

 

A total of three (3) contractors requested plans and specifications for this project, with two (2) contractors submitting bids.  M&E Contracting, Inc., will be utilizing a minority subcontractor for 5% of the work on this project.  M&E Contracting, Inc., has demonstrated that it made a good faith effort to solicit minority participation on this project.

 

 

 

Issues/Analysis: 

N/A

 

 

Budget Impact: 

The adopted FY19 budget includes funding for this project.

 

 

Options

City Council moves to approve the award of a Construction Contract with M & E Contracting, Inc.

City Council does not move to approve the award of a Construction Contract with M & E Contracting, Inc. and provides direction to staff. 

 

 

Recommended Action: 

City Council moves to approve the award of a Construction Contract with M & E Contracting, Inc.

 