City of Fayetteville
File #: 18-698    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 3/7/2019 In control: City Council Regular Meeting
On agenda: 3/25/2019 Final action:
Title: Senior Center West Construction Manager at Risk (CM@R) Contract with METCON First Guaranteed Maximum Price Amendment
Attachments: 1. Fayetteville Senior Center Milestone Dates 3-7-19.pdf, 2. GMP Amendment #1, 3. Senior Center West (Erect-Furnish Bids) 3-20-2019
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Kristoff Bauer, Deputy City Manager, ICMA-CM

FROM: Joseph Staton, Construction Manager

DATE: March 25, 2019

RE:
Title
Senior Center West Construction Manager at Risk (CM@R) Contract with METCON First Guaranteed Maximum Price Amendment
end

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
Goal 4: Desirable Place to Live, Work and Recreate


Executive Summary:
The existing CM@R contract with METCON Buildings & Infrastructure (METCON) authorizes a "pre-construction" scope of work. The execution of a Guaranteed Maximum Price (GMP) amendment is now necessary to set the construction expenses and fees, and to authorize the execution of subcontracts. Construction bids were received on March 14, 2019 and utilized in the creation of the proposed GMP Amendment #1. This is not the total cost of the project, but simply the first early bid package.


Background:
Council approved the pre-construction contract on June 25, 2018 and METCON Buildings & Infrastructure have been working in conjunction with City staff and HH Architecture to finalize plans for construction. The initial scope of work authorized in METCON's contract is for the "pre-construction" phase of the project. This focuses on cost estimation, managing the schedule, subcontractor outreach, and bidding.

Information developed during the "pre-construction" process typically culminates in the development and adoption of a GMP Amendment that will include a detailed budget, construction phase fee, and a final schedule. METCON has now developed the first GMP Amendment and a Milestone Schedule Summary for review. This GMP Amendment is for the main building structure and erection thereof. Additional GMP amendments will be prepared based on future bid packages covering the remainder of the project.


Issues/Analysis:
The main structure of the building will consist of a pre-fabricated steel structure. The manufacture and d...

Click here for full text