City of Fayetteville
File #: 19-826    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 5/17/2019 In control: City Council Regular Meeting
On agenda: 5/28/2019 Final action:
Title: Resolution of support for NCDOT to install a multi-use path and sidewalk on project U-4900, Murchison Road widening from south of Pamalee Drive to the Fayetteville Outer Loop
Attachments: 1. U4900 Bike ped RESOLUTION May 2019, 2. U4900_Proposed cross section, 3. U4900 Project limits MAP
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                            Mayor and Members of City Council

THRU:                      Kristoff T. Bauer, ICMA-CM, Deputy City Manager

 

FROM:                     Lee Jernigan, P.E., City Traffic Engineer

Sheila Thomas-Ambat, PE, CCM, CFM, Public Services Director

 

DATE:                      May 28, 2019

 

RE:

Title

Resolution of support for NCDOT to install a multi-use path and sidewalk on project U-4900, Murchison Road widening from south of Pamalee Drive to the Fayetteville Outer Loop                      

end

 

COUNCIL DISTRICT(S):                      

Council District(s)

3, 4                     

 

 

b

Relationship To Strategic Plan:

Goal IV:  Desirable place to Live, Work and Recreate

Objective C: To improve mobility and connectivity by investing in traffic flow strategies, sidewalks, trails and bike lanes

 

Executive Summary:

NCDOT is proposing to construct a widening project along Murchison Road between Pamalee Drive and the Fayetteville Outer Loop.  At the May 7, 2019 Corridor Revitalization Committee meeting, NCDOT provided options to accommodate bicycles and pedestrians along this project.  Their recommendation is to construct a ten (10’) foot wide multi-use path on the east side and a five (5’) foot wide sidewalk on the west side of Murchison Road throughout the project limits.  NCDOT is requesting approval of a resolution that the City supports these recommendations.  Upon approval NCDOT will begin design of the project including these recommendations.

 

Background: 

NCDOT is proposing to construct a widening project, U-4900, along Murchison Road between Pamalee Drive and the Fayetteville Outer Loop.  NCDOT is requesting a resolution of support by the City Council to endorse the inclusion of a ten (10’) multi-use path on the east side of the project and a five (5’) wide sidewalk on the west side of the project.  This proposal was approved by the consensus of the Corridor Revitalization Committee at their May 7, 2019 meeting.  Once NCDOT completes a conceptual design they will schedule public outreach to receive comments from local officials, business owners and other stakeholders in the area.  Currently, this public outreach is scheduled in August 2019.  Right of Way acquisition is scheduled to begin in FY 2022 and construction is scheduled to begin in FY 2024.

 

 

 

 

Issues/Analysis: 

In order to proceed with conceptual designs of this project, NCDOT is requesting approval of a resolution by City Council to support the bicycle and pedestrian improvements.  Once the resolution is approved, NCDOT will begin the scoping and design process for the project.

 

 

Budget Impact: 

There will be future costs associated with the maintenance of the sidewalk and multi-use path.  NCDOT will provide the initial capital construction costs for the multi-use path and the replacement of any existing sidewalk.  The City will be required to provide 50% of the cost of any newly constructed sidewalk along the corridor.  Final estimates of these costs are not currently known, and City Council will have an opportunity to review these costs prior to approval of a municipal agreement with NCDOT.

 

 

Options

                     Approve the resolution

                     Do not approve the resolution and provide further direction to staff

 

 

 

Recommended Action: 

Staff recommends Council approve the resolution.

 

 