City of Fayetteville
File #: 21-2043    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 6/1/2021 In control: City Council Regular Meeting
On agenda: 6/14/2021 Final action:
Title: Adoption of Capital Project Ordinance Amendment 2021-58 for Final Closeout Payment for an NCDOT Municipal Agreement for Irrigation and Landscaping Improvements on Owen Drive
Attachments: 1. CPOA 2021-58 (Owen Drive Median Municipal Agreement).pdf, 2. Owen Drive landscape Municipal Agreement #7354, 3. Owen Landscape Project map, 4. Owen Drive Landscape Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Adam Lindsay, Assistant City Manager

FROM: Sheila Thomas-Ambat, PE, CCM, CFM, Public Services Director
Lee Jernigan, PE, Assistant Public Services Director
Tracey Broyles, Budget and Evaluation Director

DATE: June 14, 2021

RE:
Title
Adoption of Capital Project Ordinance Amendment 2021-58 for Final Closeout Payment for an NCDOT Municipal Agreement for Irrigation and Landscaping Improvements on Owen Drive
end

COUNCIL DISTRICT(S):
Council District(s)
2, 5


b
Relationship To Strategic Plan:
Goal IV: Desirable Place to Live, Work and Recreate


Executive Summary:
Council is asked to adopt Capital Project Ordinance Amendment (CPOA) 2021-58 to appropriate $7,776 for a final payment to the North Carolina Department of Transportation (NCDOT) for irrigation and landscaping improvements on Owen Drive.

Council approved a Municipal Agreement (MA) for this project in August, 2017, and in February, 2019 the City received a final invoice from NCDOT for our cost share of the project. The Capital Project Ordinance was subsequently closed out in Fiscal Year 2020.

The NCDOT has now determined during its closeout and audit process that the City was not properly invoiced for our cost share on this project and has submitted an amended final billing.

Background:
With the leadership of the City Council and the Gateway Committee, the City requested NCDOT to include landscaping and irrigation in conjunction with NCDOT's median project along Owen Drive between Eastern Boulevard and Walter Reed Road. Other examples of these efforts include the Ramsey Street, Glensford Drive and Grove Street/Eastern Blvd projects.

On November 18, 2016, Council adopted CPO 2017-20 for the estimated $100,000 total project cost. The CPO was adopted in advance of receipt of the municipal agreement to allow for the City to contract with PWC to install the required water taps for the irrigation system during NCDOT's construction phase...

Click here for full text