Title: Approval for City Manager to Execute a Construction Contract with Muter Construction for the Mazarick Park Tennis Center Building
Attachments: 1. Re-Advertisement Bid Tab - Mazarick park Tennis Center Building
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Douglas J. Hewett, ICMA-CM, City Manager
Adam Lindsay, Assistant City Manager

FROM: Kimberly Toon, CLGPO, Purchasing Manager
Michael Gibson, Parks, Recreation, and Maintenance Director
Robert Stone, PE, Construction Management Department Director

DATE: September 26, 2022

RE:
Title
Approval for City Manager to Execute a Construction Contract with Muter Construction for the Mazarick Park Tennis Center Building
end

COUNCIL DISTRICT(S):
Council District(s)
District 2


b
Relationship To Strategic Plan:
Goal 4 - The City of Fayetteville will be a highly desirable place to live, work and recreate with thriving neighborhoods and a high quality of life for its citizens.


Executive Summary:
City Council is asked to authorize the City Manager to execute a construction contract with the apparent lowest responsive, responsible bidder, Muter Construction, for the Mazarick Park Tennis Center Building in the amount of $2,340,525.

Background:
On March 15, 2016, Fayetteville voters passed a $35 million bond referendum for parks and recreation projects including several new projects as well as renovations to a few existing parks and facilities. Since voters approved the bond package, several projects have been completed and several more are currently under construction or under design.

Included in the bond package was a Tennis Center planned for Mazarick Park. CRA Associates, Inc. was awarded the site design contract by Council in April 2021 and the Tennis Center Clubhouse design was awarded to Summit Design through an existing General Services Contract.

The Site Work for the Mazarick Park Tennis Center (including all clearing and grubbing, grading, infrastructure, utilities, stormwater, parking lot, driveway, sidewalks, and landscaping) was awarded by Council on June 13, 2022, and is currently underway. The construction of the tennis and pickleball courts as well as the lighting will be pu...

Click here for full text