Title: Accept NCDOT Grant for Terminal Improvement, Additions to the North and South General Aviation (GA) Facilities, and Equipment Purchase and Adopt Capital Project Ordinance Amendment 2024-7 and Capital Project Ordinance 2024-9 COUNCIL DISTRICT(S):
Attachments: 1. FY24 NCDOT Notification of Funding Allocation, 2. CPO 2024-9, 3. CPOA 2024-7 (CPO 2023-8)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Kelly Olivera, Assistant City Manager

FROM: Alvester T. (Toney) Coleman, PhD, A.A.E., Airport Director
Kimberly Leonard, CLGFO, CLGBO, CPA, MPA, Budget and Evaluation Director

DATE: November 27, 2023

RE:
Title
Accept NCDOT Grant for Terminal Improvement, Additions to the North and South General Aviation (GA) Facilities, and Equipment Purchase and
Adopt Capital Project Ordinance Amendment 2024-7 and Capital Project Ordinance 2024-9

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
Goal IV - Desirable Place to Live, Work and Recreate
4.1 - To maintain public transportation investments with high-quality transit and airport services.

Executive Summary:
Council is asked to adopt Capital Project Ordinance Amendment (CPOA) 2024-7 to appropriate and additional $1,858,191 for the Terminal Renovations Phase III project, and Capital Project Ordinance (CPO) 2024-9 to appropriate $640,105 for a general aviation access control system upgrade, south general aviation self-fueling station development, a digital display wall installation, general aviation septic system upgrade, a bucket truck, and related ancillary costs.

The source of funding for the requested appropriations is a grant from the North Carolina Department of Transportation's Division of Aviation (NCDOT DOA) in the amount of $2,498,296.

Background:
On August 8, 2022, the council adopted Capital Project Ordinance 2023-08 to fund Terminal Renovations Phase III using $1,870,450 of Federal Aviation Administration Airport Improvement Program dollars. An additional $1,858,191 of funding for this project will come from the FY24 NCDOT DOA grant. Therefore, CPOA 2024-7 will amend CPO 2023-8 to provide total funding for this project of $3,728,641.

CPO 2024-9 will appropriate $640,105 of the NCDOT DOA grant award for the following projects:

* $200,105 - General Aviation Access Control System Upgrade
* $140,000 - Digita...