Title: Award of Terminal Renovations Phase III Construction Contract to Daniels & Daniels Construction Company, Inc., and Authorization for the City Manager to Execute the Contract COUNCIL DISTRICT(S):
Attachments: 1. FAY Part 3 Bid Tabulation, 2. Contract for Daniels & Daniels Construction Company, Inc.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Kelly Olivera, Assistant City Manager

FROM: Deontae K. Watson, MBA, A.A.E., Interim Airport Director
Kimberly Toon, CLGPO, Purchasing Manager


DATE: January 8, 2024

RE:
Title
Award of Terminal Renovations Phase III Construction Contract to Daniels & Daniels Construction Company, Inc., and Authorization for the City Manager to Execute the Contract

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
Goal IV - Desirable Place to Live, Work and Recreate
4.1 - To maintain public transportation investments with high quality transit and airport services.

Executive Summary:
Council is asked to award the contract for construction of Terminal Renovations Phase III to Daniels & Daniels Construction Company, Inc.as the successful bidder of the bid process completed September 12, 2023.

Background:
Council adopted Capital Project Ordinance 2023-8 on August 8, 2022, which appropriated $1,870,450 of Federal Aviation Administration Airport Improvement Program dollars to fund Terminal Renovations Phase III. The project was advertised for bid on August 15, 2023, however, the initial bid process only received one bidder, thus requiring a second bid process. The bids received in the second bid process on September 12, 2023 came in above budget. To provide the additional funds needed, Council adopted Capital Project Ordinance Amendment 2024-7 on November 27, 2023, which appropriated $1,858,191 of funding from the North Carolina Department of Transportation to the project budget, for a total budget of $3,728,641.

Funding for the Terminal Renovations Phase III project will be used for:
o The upfit of 1,226 square feet of space formerly utilized by American Airlines for baggage into new airline ticketing offices,
o The re-roofing of 41,152 of square feet over Concourse B,
o The addition of 600 square feet to Concourse B seating and floor area between Gate 4 and Gate 5 with stora...