TO: Mayor and Members of City Council
THRU: Timothy L. Bryant, CEO/General Manager
Fayetteville Public Works Commission
FROM: Fayetteville Public Works Commission
DATE: March 14, 2024
RE:
Title
PWC - Bid Recommendation - Cross Creek and Rockfish Creek Water Reclamation Facilities Screw Pump Improvements
end
COUNCIL DISTRICT(S):
Council District(s)
All
b
Relationship To Strategic Plan:
High Quality Built Environment
Executive Summary:
Bids were received for the Cross Creek Water Reclamation Facility and Rockfish Creek Water Reclamation Facility Screw Pump Improvements. The lowest responsive, responsible bidder is T. A. Loving Company, Goldsboro, NC, in the total amount of $19,139,750.00.
Background:
The Fayetteville Public Works Commission, during their meeting on February 28, 2024, approved the bid recommendation to award the Cross Creek Water Reclamation Facility and Rockfish Creek Water Reclamation Facility Screw Pump Improvements to T. A. Loving Company, Goldsboro, NC, the lowest responsive, responsible bidder, in the total amount of $19,139,750.00. The Commission also approved to forward this recommendation to City Council for approval.
Bids were received February 8, 2024, as follows:
Bidders Total Base Bid Alternate Bid Total Base
Bid Item No. 1 Bid + Alternate Bid
T. A. Loving Company, Goldsboro, NC $17,013,250.00 $2,126,500.00 $19,139,750.00
J. Cumby Const, Cookeville, TN $17,532,500.00 $1,900,000.00 $19,440,500.00
Crowder Construction, Apex, NC $18,183,700.00 $1,265,500.00 $19,449,200.00
Issues/Analysis:
Notice of the bid was advertised through PWC's normal channels on December 11, 2023, with an original bid date of January 18, 2024, which was extended to February 8, 2024. Bids were solicited from three (3) vendors and three (3) were received.
Budget Impact:
Project is budgeted in 002.0160.0435.2210463-01.820090CPR100499
Options:
N/A
Recommended Action:
The Fayetteville Publ...