Title: Professional Service Contract Execution Recommendation - Phase II Part B Watershed Study for Cross Creek
Attachments: 1. CRO Phase IIB WA
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Adam Lindsay, Assistant City Manager

FROM: Sheila Thomas-Ambat, Public Services Director
Alicia Lanier, Stormwater Project Manager Special Projects

DATE: March 14, 2024

RE:
Title
Professional Service Contract Execution Recommendation - Phase II Part B Watershed Study for Cross Creek
end

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
Goal 1: Safe and Secure Community
Goal 3: High Quality Built Environment
Goal 4: Desirable Place to Live, Work and Recreate


Executive Summary:
Council is asked to authorize the execution of an engineering service contract for professional services for $651,885.00 for Phase II Part B Watershed Study for Cross Creek as part of the Watershed Master Plan program to the consulting firm Hazen Sawyer.

This qualification-based selection of Hazen Sawyer is utilizing the City's On-Call Professional Engineering Services for Comprehensive Stormwater Watershed Studies.

Background:
Hazen Sawyer has provided professional services to the Watershed Master Plan program since the beginning.

Budget for professional services for this was included in Council's adopted FY24 budget utilizing Stormwater Enterprise Funds.


Issues/Analysis:
None


Budget Impact:
There is no impact to the General Fund. Budget for Phase II Part B Watershed Study for Cross Creek as part of the Watershed Master Plan program was included in Council's adopted FY24 budget utilizing Stormwater Enterprise Funds.


Options:
1. Authorize the execution of an engineering service contract for professional services for $651,885.00 for Phase II Part B Watershed Study for Cross Creek as part of the Watershed Master Plan program to the consulting firm Hazen Sawyer.
2. Do not authorize the execution of an engineering service contract for professional services for $651,885.00 for Phase II Part B Watershed Study for Cross Creek as part of the Watershed Master Plan program to th...

Click here for full text