City of Fayetteville
File #: 24-3848    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 2/12/2024 In control: City Council Regular Meeting
On agenda: 3/25/2024 Final action:
Title: Adoption of Capital Project Ordinance Amendment 2024-17 to Reappropriate Funds and Adopt the Capital Project Ordinance 2024-16 to move the Funding to the Winslow St / Russell St Parking Lot Improvements and Award the Construction Contract to Lanier Construction Company, Inc.
Attachments: 1. Replacement Parking for City Employees Expense Report, 2. Replacement Parking for City Employees Revenue Report, 3. CPOA 2022-30, 4. Replacement Parking For City Employees (Pkg Opt 1 Winslow and Russell), 5. Legends Avenue Improvement ITD Remaining Budget, 6. CPOA 2024-16, 7. Bid Tab - Winslow Street Parking Lot, 8. Winslow St Parking Layout, 9. CPOA 2024-17
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Members of City Council

THRU: Douglas J. Hewett, ICMA-CM, City Manager

FROM: Adam Lindsay, Assistant City Manager
Kimberly Leonard, CLGBO, CLGFO, CPA, MPA, Budget & Evaluation Director
Rob Stone, PE, Construction Management Director

DATE: March 25, 2024

RE:
Title
Adoption of Capital Project Ordinance Amendment 2024-17 to Reappropriate Funds and Adopt the Capital Project Ordinance 2024-16 to move the Funding to the Winslow St / Russell St Parking Lot Improvements and Award the Construction Contract to Lanier Construction Company, Inc.
end

COUNCIL DISTRICT(S):
Council District(s)|109|


b
Relationship To Strategic Plan:
Goal 3: High-Quality Built Environment
Goal 4: Desirable Place to Live, Work, and Recreate

Executive Summary:
Council is asked to adopt Capital Project Ordinance Amendment (CPOA) 2024-17 to re-appropriate $546,000 from the completed Legend Ave Extension Project and adopt CPOA 2024-16 to move the funds to the Winslow St / Russell St Parking Lot Improvements, and to award the construction contract to Lanier Construction, Inc, the apparent lowest responsive, responsible bidder. The project will add 50 new parking spaces to the existing lot, for a total of 86 spaces.

Background:
The City of Fayetteville Winslow St / Russell St Parking Improvements are needed as this will provide additional employee parking during normal work hours and additional public parking after hours and during weekends and holidays. The project was put out for bid in August of 2022, but bids came back over budget. After discussions with Public Services, it was determined that the remaining funds from the completed Legend Ave Extension Project could be utilized to complete the project. The project was rebid in January of 2024, and bids came back as follows, with Lanier Construction, Inc. as the apparent lowest responsive, responsible bidder:

BIDDER TOTAL COST

Lanier Construction, Inc. $568,513.50