TO: Mayor and Members of City Council

THRU: David W. Trego, CEO/General Manager
Fayetteville Public Works Commission

FROM: Fayetteville Public Works Commission

DATE: August 13, 2018

RE:
Title
Bid Recommendation - Annual Lighting LED Upgrade and Replacement
end

COUNCIL DISTRICT(S):
Council District(s)
All


b
Relationship To Strategic Plan:
High Quality Built Environment


Executive Summary:
Bids were received for the Annual Lighting LED Upgrade and Replacements. The recommended lowest responsive, responsible bidder is Pike Electric, LLC, Mount Airy, NC, in the total amount of $1,704,614.85.


Background:
The Fayetteville Public Works Commission during their meeting on July 25, 2018, approved the bid recommendation to award the contract for the Annual Lighting LED Upgrade and Replacements to Pike Electric, LLC, Mount Airy, NC, the lowest responsive, responsible bidder in the total amount of $1,704,614.85 and to forward to City Council for approval.

Bids were received on July 10, 2018, as follows:

Bidders Total Cost

Pike Electric, LLC, Mount Airy, NC $1,704,614.85
Lee Electric, Aberdeen, NC $5,062,277.00
CW Wright, Chesterfield, VA $6,101.683.30


Issues/Analysis:
The purpose of this contract is to complete the LED light removal and installations throughout the service area. This project was advertised twice due to receiving an insufficient number of bids on the first advertisement. The lowest responsive, responsible bidder is recommended. Pike Electric, LLC held the previous LED Light Installation Contract.

SDBE/DBE/HUB Participation: Pike Electric, LLC will be self-performing installations. Staff will monitor contract to ensure local businesses and disadvantaged businesses are utilized when subcontracting opportunities arise.



Budget Impact:
Funds are budgeted in the following: FY2019 - CIP EL 3 - Streets Lights - LED Conversion -$750,000; FY2019 - CIP EL 4 - LED Area Lights - New Installat...