TO: Mayor and Members of City Council
THRU: David W. Trego, CEO/General Manager
Fayetteville Public Works Commission
FROM: Fayetteville Public Works Commission
DATE: October 8, 2018
RE:
Title
Bid Recommendation - Beaver Creek Outfall Rehabilitation Phase I
end
COUNCIL DISTRICT(S):
Council District(s)
All
b
Relationship To Strategic Plan:
High Quality Built Environment
Executive Summary:
Bids were received for the Beaver Creek Outfall Rehabilitation Phase I project. The recommended lowest responsive, responsible bidder is Insituform Technologies, LLC, Chesterfield, MO, in the total amount of $2,240,880.00.
Background:
The Fayetteville Public Works Commission during their meeting on September 26, 2018, approved the bid recommendation to award the contract for the construction of Beaver Creek Outfall Rehabilitation Phase I to Insituform Technologies, LLC, Chesterfield, MO, the lowest responsive, responsible bidder in the total amount of $2,240,880.00 and to forward to City Council for approval.
Bids were received on September 11, 2018, as follows:
Bidders: Total Cost
Insituform Technologies, LLC, Chesterfield, MO $2,240,880.00
Granite Inliner, Gastonia, NC $2,937,425.00
IPR Southeast, Stone Mountain, GA $3,552,230.00
SAK Construction, O'Fallon, MO $3,984,975.00
Issues/Analysis:
Plans and specifications were requested by six (6) contractors with four (4) contractors responding. Insituform Technologies, LLC was deemed the lowest responsive, responsible bidder. Local Participation: Insituform Technologies, LLC, will utilize Taylors Grading and Utility, Fayetteville, NC for site work, grading and seeding. Sunbelt Rentals, Fayetteville NC will be utilized for equipment needs.
Budget Impact:
Funds are budgeted in FY2019 CIP WS80 - Beaver Creek Outfall Rehabilitation Phase I - $2,490,000.00 was budgeted for construction of this project.
Options:
N/A
Recommended Action:
The Fayetteville Public ...